More than 6000 kms of border roads to be constructed during 2016-18

Ministry of Defence   03-May, 2016 13:30 IST

Border Roads Organisation (BRO) is entrusted with 837 roads measuring 29,417 km for construction/ maintenance. The State wise details of these roads in the country are as below:

 

S. No

State

Nos of Roads

Length in Km

 

i

Andaman and Nicobar

1

23.94

 

ii

Arunachal Pradesh

138

6215.25

 

iii

Assam

7

194.22

 

iv

Himachal Pradesh

23

1068.93

 

v

Jammu and Kashmir

364

9296.88

 

vi

Manipur

22

1851.51

 

vii

Mizoram

15

1046.50

 

viii

Nagaland

16

1018.20

 

ix

Punjab

20

330.97

 

x

Rajasthan

134

5462.85

 

xi

Sikkim

60

1196.47

 

xii

West Bengal

3

110.80

 

xiii

Tripura

6

469.54

 

xiv

 Uttrakhand

28

1131.01

 

Total

837

29417.07

 

Approx.

29,417

 

519 roads of length measuring 22,225 km are under construction /improvement by BRO. Out of which, 21 roads of length measuring 967 km have been completed. The completion schedule of the balance roads is as under: 

·         2016                                  -           44 roads (1391 km)

·         2017                                  -           65 roads (1758km)

·         2018                                  -           91 roads (2947km)

·         Beyond 2018                     -           298 roads (15,162 km)

 There are certain delays in execution of road projects mainly due to the following reasons:

·         Delay in Forest/Wildlife clearance

·         Hard rock stretches.

·         Limited working season.

·         Difficulties in availability of construction material.

·         Delay in land acquisition.

The cost incurred by BRO in the last three years on construction of border roads and maintenance is given below:

 

Year

Construction / improvement of roads                       (Rs in Crores)

Maintenance of roads                     (Rs in Crores)

2013-14

3009

634

2014-15

2814

688

2015-16

upto February 2016

2573

571

 


Cost escalation due to time over run   is considered on case to case basis. However, escalation of cost year wise due to delay in construction is not maintained separately for  the works under taken by BRO.   


BRO undertakes works on roads through departmental execution by utilizing its own resources. However, some stretches of roads, few bridges and tunnels are executed through outsourcing.

Comments

Popular posts from this blog

Series of steps announced by NHAI to remove Hurdles for Faster Execution of Projects

Ministry of Road Transport & Highways                                03-May, 2016     12:45 IST Ministry of Road Transport & Highways announced few basic measures to improve speed of execution of road projects under National Highways Authority of India (NHAI). To speed up the projects, NHAI has delegated powers to its Regional Officers for hiring of equipment and laborers up to Rs.10 lacs per project , to demolish structures that fall within the right-of-way of the project. As some of the contracts had no provision for demolition of such structures, there would often be protracted correspondence between the contractors, Project Directors and NHAI headquarters before these could be removed, often leading to delay in execution of projects . With this delegation of power to ROs NHAI will be able to make encumbrance free land available more speedily to the concessionaire/contractors as laid down under the concession agreement or contract. The Regional Offic...

What are the women specific programs in Scientific Research and Development in India?

05-May-2016 16:41 IST Women Participation in Scientific Research and Development Department of Science And Technology (DST) initiated exclusive schemes to enable women to pursue a career in Research and Development (R&D) in Science and Technology (S&T) only in the year 2002. Before that sporadic attempts had been made in this direction and hence only a few women were engaged in R&D in mainstream science. One of the major reasons for this anomaly leading to gender gap in scientific R&D was the break in career that many women had to face due to familial compulsions like marriage, child birth, looking after old or ailing parents, children's education and so on. Subsequently, DST launched DISHA Programme for Women in Science to address these issues and made focused efforts to not only facilitate the re-entry of such women to mainstream science by offering them opportunities to pursue R&D, take up projects having distinct societal impact and explore a career in Int...